The Expanding Project Progressing as Planned

At the beginning of April, all works on the expanding projects has been progressing well. The equipment installations of the water-cooling system, purging system, hydraulic system and batching system, proceeding by KingHun Electronics, are estimated to be completed by April 25. The installation of the electrical control system (low-pressure control) and the proportioning belt,  that are in the charge of company's own installation team, will be finished respectively by the 20th and 18th. The overall equipment tests are expected to be carried out between April 25th and 30th, after which the construction of furnace will start.